Constraints
Criteria
- Budget - $250,000 (total materials + permitting + construction)
- Protect existing infrastructure (culverts, utilities, sewer line, etc.)
- Finish project design by mid Spring
- Abide by all laws in the state of Virginia
- Design for a stable stream channel for less than a 10 year flood
Criteria
- Repair/prevent channel erosion
- Keep the park aesthetically pleasing
- Eliminate slope failures of stream banks
- Reestablish native vegetation on stream banks
- Follow engineering standards
- Educate public about stream restoration